Comparison
Design-bid-build vs. design-build for tenant improvements
The delivery method decides who holds the drawings, who carries the price risk and how much time sits between lease signing and opening day.

Design-bid-build
The tenant hires the architect, who completes the permit set. Two to four general contractors bid the same documents; the tenant signs with the best-value GC. Architect and contractor are separate contracts with the tenant.
Design-build
One contract with a design-build contractor who employs or subcontracts the architect and engineers. Pricing develops with the design, often as a guaranteed maximum price (GMP) once drawings are far enough along.
Side-by-side
| Design-bid-build | Design-build | |
|---|---|---|
| Schedule | Sequential: design → bid (2–4 weeks) → construction | Overlapping: pricing, permitting and long-lead procurement start during design — often 3–6 weeks faster |
| Price competition | Strong — several GCs bid identical, complete documents | Limited — competition happens on fee and general conditions, or not at all |
| Architectural control | The architect works for the tenant and reviews the GC’s work | The designer works for the builder; value engineering can quietly change scope |
| Change-order exposure | Gaps in documents become change orders; complete permit sets keep them low | Fewer design-error change orders, but a GMP carries contingency you pay for |
| Single point of responsibility | No — design and construction are separate | Yes — one contract for both |
| Best for | Larger or complex build-outs, tenants who want price certainty from competitive bids | Small, repeatable suites, tight rent-commencement dates, owners with a trusted builder |
Suites under 5,000 SF
Small office and retail TIs are often simple enough that design-build’s speed outweighs the loss of bid competition — especially second-generation suites where the scope is mostly finishes, lighting and a few walls. Ask for an open-book GMP and keep an independent test fit as the scope baseline.
Larger or complex build-outs
Above roughly 5,000 SF — or in any restaurant, clinic or cold-shell project — the dollars at stake make competitive bidding on a complete, coordinated permit set worth the extra weeks. Complete documents are also what keep change orders under control once construction starts.
A hybrid that works for many tenants
Bring a GC in during design development under a preconstruction agreement to price the schematic layout, flag long-lead items and check constructability — then finish the permit set independently and either negotiate with that GC or bid it. You keep the architect on your side, gain the schedule benefit of early pricing, and preserve the option to compete the work.
See what a complete permit set contains, or compare who the architect works for.